Other Resources My Cup of Joe » Contractor Question - WWCOJD Rss Feed  
Moderators: k9car363, the bear, DerekL, alicefoeller Reply
2009-10-07 1:28 PM

User image

Extreme Veteran
474
1001001001002525
W. Michigan
Subject: Contractor Question - WWCOJD
This might be a bit long.  My question will be at the end of this rant.

My wife & I are getting to the end of remodeling our house.  The one room left is the back entryway that leads either up to the kitchen or down to the basement.  It had the same old, faded linoleum that we tore out of the kitchen and we wanted to tile it with the same tile we used when re-doing the kitchen.  I'd do it myself (I tiled the kitchen and two bathrooms in the house) but the stairs seemed like more of a challenge that I wanted right now with a 5 month old baby and a demanding job. 

We got a couple quotes and decided on a one-man operation who offered the middle of the road quote.  He said he'd start Monday and be finished by Wednesday and asked that we pay him 1/2 up front.  He started on Monday afternoon, two weeks ago, tearing up the linoleum.  When we spoke he said that he'd be back 1st thing Tuesday to lay the tile.  We never heard from him or saw him at all Tuesday.  He showed up Wednesday afternoon with three sob stories where 1) his car broke down 2) he got upset at his car and threw & broke his cell phone and 3) was sick Tuesday.  He got 1/2 the area tiled on Wed, and came Thursday afternoon (said he'd be there 1st thing) to tile the rest.  We spoke that evening and he said he'd be there Friday to grout, and asked for the balance of his payment.  I came home for lunch Friday, he hadn't been there.  I got home from work Friday, he hadn't been there.  I left a message for him, which he returned later that evening, giving me sob story #4 for the week.   At that point, he said he'd be there Saturday at 2 to grout.  Saturday afternoon came & went with no call and no show.  We left him a message that if we didn't hear from him by the end of the day to consider himself fired from the job and that we wouldn't pay him anything further. 

Here's the issue, what should I do with the tools that he left behind at our house?  They're mostly hand tiling tools & buckets, maybe $50 total, but also a heavy duty electric angle grinder.  I left a message last Sunday for him to call me to arrange to pick up his tools and haven't heard a word from him.

I look forward to receiving the infinite wisdom of COJ......


2009-10-07 1:44 PM
in reply to: #2447934

User image

Veteran
667
5001002525
Subject: RE: Contractor Question - WWCOJD
Those tools are not your property.  You must return his tools when/if he comes and asks for him.  You need to give him a reasonable amount of time before you dispose of these tools.  I would recommend something along the lines of "you have until after (probably a week) to retrieve your tools.  If you do not retrieve your tools, we will consider them abandoned and will not be responsible for them."  Keep a copy or log of whatever you say/or write to him.

Don't give him the option to arrange a pick up because he can string you on forever.  You give him a definitive deadline to respond and once that time has passed, I would probably donate or throw out the gear.
2009-10-07 1:49 PM
in reply to: #2447934

User image

Extreme Veteran
357
1001001002525
Ft. Myers, Florida
Subject: RE: Contractor Question - WWCOJD
If you have an address for him, I almost think it would be worth the drive across town to return them yourself.  I understand that you should not have to do that but it may be worth it to just be done with him.  Be thankful if he doesn't start hounding you for more money.
2009-10-07 2:02 PM
in reply to: #2447934

Master
2009
2000
Charlotte, NC
Subject: RE: Contractor Question - WWCOJD
I would send him a letter that requires a signature upon delivery stating you want the tools out of your house by a certain date or you will do XYZ with them.  I would also hold onto the signatire confirmation.
2009-10-07 3:08 PM
in reply to: #2447934

User image

Mountain View, CA
Subject: RE: Contractor Question - WWCOJD
Is this guy originally from California? I think he did started some work on my parents' house a couple of years ago. Only instead of a few weeks, it was a saga of several months.

The signature-upon-delivery letter sounds like a good plan. Going to his house to deliver the tools might also work, and that would give you a chance to make him talk to you face to face. (Of course, he might not answer the door, or might have a family member answer.)

Whatever you do about the tools, if this guy has a contractor's license (or if he says he does), file a complaint with the state board.
2009-10-07 3:25 PM
in reply to: #2448181

User image

Member
1699
1000500100252525
Subject: RE: Contractor Question - WWCOJD
My brother is a contractor and I resent the implication that all contractors are irresponsible and untrustworthy. When my brother says he will be somewhere, he will be there within an hour or so of when he said. Most of the time. If there it was league night the night before, then probably a little longer.

I am kidding, partially. My brother really is a contractor and he is not particularly punctional. I have worked with him a few times, and compared to most of his peers, he is a stinking swiss watch. That whole industry is full of guys who would be fired, or have been fired, in corporate America.



2009-10-07 3:52 PM
in reply to: #2447934

User image

Veteran
172
1002525
Seattle
Subject: RE: Contractor Question - WWCOJD
I'm not an attorney, but it seems to me you have two options:

1.  Keep the tools until he completes the job contracted for (you do have a written contract don't you?) and you have paid for.  If you sell the tools, he will probably be able to sue you for replacement tools which will probably be more than you received; or

2.  Hire another contractor to complete the work and then take the original tile layer to small claims court for the cost of the second contractor completing the job.

In the event he is not bonded and you don't have a written contract, you are probably SOL.
2009-10-07 5:24 PM
in reply to: #2448291

User image

Extreme Veteran
930
50010010010010025
Fort Worth, TX
Subject: RE: Contractor Question - WWCOJD
d2lock - 2009-10-07 3:52 PM

I'm not an attorney, but it seems to me you have two options:

1.  Keep the tools until he completes the job contracted for (you do have a written contract don't you?) and you have paid for.  If you sell the tools, he will probably be able to sue you for replacement tools which will probably be more than you received; or

2.  Hire another contractor to complete the work and then take the original tile layer to small claims court for the cost of the second contractor completing the job.

In the event he is not bonded and you don't have a written contract, you are probably SOL.


I don't think he ever received full payment. They can still apply the remaining half to the new contractor that finishes the work.

2009-10-07 6:23 PM
in reply to: #2447934

User image

Extreme Veteran
3177
20001000100252525
Subject: RE: Contractor Question - WWCOJD
My F-I-L is a licensed electrician who owns his own business. He is always there unless he is in the hospital, and sometimes even then. He also does a few general jobs as well but mostly electrical. Not quite the same I know but...there you go.

As for your case I would say get his signiture on a letter, return letter, fed ex etc that shows he has recieved a letter which indicates when he needs to get the tools by and how to pick them up. Give him a reasonable amount of time (1-2 weeks) and if they are not taken I would donate them to a goodwill or such. It sounds like you paid him for half and he did about that much. Honestly if you did the rest of the tile in the house you could probably grout it yourself pretty easily as the hard part of entryway/stairs is generally getting the tiles cut and laid properly.

In reality there is probably not much you can do other than what has previously been mentioned by other posters.
2009-10-08 1:15 AM
in reply to: #2448546

User image

Regular
102
100
Auckland, New Zealand
Subject: RE: Contractor Question - WWCOJD
You're all too politically correct. There were no tools. Nup, you didnt see any tools, right?
2009-10-08 6:32 AM
in reply to: #2447934

User image

Master
2006
2000
Portland, ME
Subject: RE: Contractor Question - WWCOJD
The abandon property law in my state is after you notify the contractor, he has 14 days to claim his stuff. If the value of the property is under $500 you can toss it. If it is more than you must store it.

On the contractor, I deal with them for a living and it is very important to check references. Also, on residential property, you must have a written contract if it is over a certain amount.

Always being behind in the payment like you did is a good thing. However 50% down is a huge red flag for such a small project. It means that he has zero credit at the store and zero cash flow. I would never hire a contractor under that condition unless I had a leash around his neck and I put a performance clause in the contract.




2009-10-08 8:24 AM
in reply to: #2447934

Expert
763
5001001002525
Behind you
Subject: RE: Contractor Question - WWCOJD
He'll need that grinder sooner or later, so when he comes back, buts his as$ with it!  Lazy as$ rednecks!
2009-10-08 11:42 AM
in reply to: #2448226

User image

Master
1641
100050010025
Seattle, California
Subject: RE: Contractor Question - WWCOJD
eberulf - 2009-10-07 1:25 PM My brother is a contractor and I resent the implication that all contractors are irresponsible and untrustworthy. When my brother says he will be somewhere, he will be there within an hour or so of when he said. Most of the time. If there it was league night the night before, then probably a little longer. I am kidding, partially. My brother really is a contractor and he is not particularly punctional. I have worked with him a few times, and compared to most of his peers, he is a stinking swiss watch. That whole industry is full of guys who would be fired, or have been fired, in corporate America.


I agree.  I worked for a larger general contractor and the work we did was always top notch.  As well we would always come back and address any issues within a week and fix any problems valid or not until the client was happy. 

There are contractors out there but it's not all bad like you see on TV.  There are a lot of honest people who do very good work.  
2009-10-08 12:07 PM
in reply to: #2447934

User image

Extreme Veteran
474
1001001001002525
W. Michigan
Subject: RE: Contractor Question - WWCOJD
We were spoiled by the other contractors that we've worked with and didn't perform the due diligence that we should have on this guy.

Well, the mystery's solved.  He left me a VM over lunch.  He's mad at me now since after his performance last week that I didn't assume something was wrong and that he wasn't blowing me off.  Turns out he was in jail.....Awesome.....

More to follow...
2009-10-08 12:17 PM
in reply to: #2449758

User image

Alpharetta, Georgia
Bronze member
Subject: RE: Contractor Question - WWCOJD
madcap95 - 2009-10-08 12:07 PM We were spoiled by the other contractors that we've worked with and didn't perform the due diligence that we should have on this guy.

Well, the mystery's solved.  He left me a VM over lunch.  He's mad at me now since after his performance last week that I didn't assume something was wrong and that he wasn't blowing me off.  Turns out he was in jail.....Awesome.....

More to follow...


Why on earth would he be mad at YOU? Cause you're not a mind reader and didn't check the jail registrar?
But this story is getting better and better! To read... not necessarily for you

 
2009-10-08 12:37 PM
in reply to: #2447934

User image

Elite
2552
20005002525
Evans, GA
Subject: RE: Contractor Question - WWCOJD
Ask him if there is a work release program ba-dump-bump!


2009-10-08 12:38 PM
in reply to: #2447934

User image

Champion
6786
50001000500100100252525
Two seat rocket plane
Subject: RE: Contractor Question - WWCOJD

Back in the day when I was a carpenter (yes, really) we had a standing joke about "waiting for the tile guy" We'd bet on the day he would show up, not the week or the month, but the day. Tuesday was the money.

 

2009-10-08 12:52 PM
in reply to: #2449758

User image

Extreme Veteran
3177
20001000100252525
Subject: RE: Contractor Question - WWCOJD
madcap95 - 2009-10-08 10:07 AM We were spoiled by the other contractors that we've worked with and didn't perform the due diligence that we should have on this guy.

Well, the mystery's solved.  He left me a VM over lunch.  He's mad at me now since after his performance last week that I didn't assume something was wrong and that he wasn't blowing me off.  Turns out he was in jail.....Awesome.....

More to follow...


Oh thats rich. Not your fault he got arrested. He did something to land himself there I would guess so it is his fault if he lost your business and the other half of the money for not finishing the job.
2009-10-08 1:49 PM
in reply to: #2447934

User image

Extreme Veteran
474
1001001001002525
W. Michigan
Subject: RE: Contractor Question - WWCOJD
I wish there was a way to upload the VM message here, it's classic.  To recap:

1) Car broke down
2) broke his phone
3) got sick
4) got sent to jail
5) got fired

If a dog dies somewhere, I think we have a country song on our hands here....
2009-10-08 2:08 PM
in reply to: #2447934

User image

Elite
3090
20001000252525
Spokane, WA
Subject: RE: Contractor Question - WWCOJD

Wow, what a great story. I'm going to assume he won't be giving your name as a reference.

New Thread